Environmental and Social Impact Assessment
1 EXECUTIVE SUMMARY
1.1 Project Description
Abu Dhabi Water & Electricity Company (ADWEC) forecasts the growth in electrical demand in Abu Dhabi will require an additional 4,500 megawatts (MW) of electrical generation capacity by 2017 and 21,000 MW by 2030. ADWEC forecasts that the need for additional desalinated water will grow to require an additional 200 million Imperial gallons per day (MIGD) by 2017 and 550 MIGD by 2030. The Mirfa Independent Water and Power Project (IWPP) is a critical component of the Abu Dhabi Water & Electricity Authority’s (ADWEA) plans to meet these future demands for electricity and water.
The Mirfa IWPP will be constructed at the existing Mirfa Power and Desalination Complex located at Mirfa in the Al Gharbia region of Abu Dhabi Emirate. The Al Mirfa Power and Desalination Plant is currently location on this site owned and operated by Al Mirfa Power Company (AMPC), a subsidiary of ADWEA. This existing facility will be decommissioned and some of its equipment and facilities integrated into the Mirfa IWPP.
ADWEA will turn over portions of the existing plant and facilities to International Power S.A. – Dubai Branch (GDF Suez Group) as the IWPP developer Branch (GDF SUEZ Group) as the IWPP developer who will remove or rehabilitate and reuse existing facilities on the site as well as construct new facilities for the expansion of the plant. The developer and ADWEA will form the Mirfa Project Company (MPCo) to jointly build, own, and operate the facility.
The proposed net power capacity of Mirfa IWPP will be 1600 MW, of which 360 MW will be provided by open cycle gas turbines (OCGT) and 1,240 MW by combined cycle gas turbines (CCGT). The gross water capacity of the Mirfa IWPP will be 52.5 MIGD. The capacity will be achieved by maintaining existing multi-stage flash (MSF) units (22.5 MIGD) in service and adding new sea water reverse osmosis (SWRO) plant (30 MIGD). One area of the site will be retained by ADWEA, with the equipment within this area being removed from service and decommissioned.
The existing Mirfa Plant has a net power capacity of 140 MW and a desalination capacity of 38.7 MIGD. This plant was completed in two phases (A and B) as follows:
· Phase A was commissioned in 1995-96, and consisted of four Siemens gas turbines (GT), each having a gross capacity of 48 MW, operating in combined cycle, supplying steam to three Ansaldo MSF desalination units with a combined capacity of 16.2 MIGD. Two auxiliary boilers provide operational flexibility.
· Phase B, commissioned in 2001-02, comprises three Fisia MSF units producing a net desalination capacity 22.5 MIGD of water (7.5 MIGD per unit). The process steam for these MSF units is provided by two auxiliary boilers.
Phase A infrastructure will be decommissioned by ADWEA as part of the implementation of the Project. Decommissioning procedures will be addressed in a separate Decommissioning Environmental Management Plan (DEMP) to be submitted by ADWEA.
Phase B will be transferred to MPCo and form part of the overall Mirfa IWPP. Common facilities, buildings and systems to be transferred to MPCo for further common use of the Mirfa IWPP include:
· Seawater screening and pumping station; · Seawater chlorination and switchgear building; · Demineralization plant; · Auxiliary boilers; · Fuel systems; · Remineralization plant; · Distillate treatment plant, limestone storage area and distillate tank; · Potable water tanks; · Auxiliary systems of existing Phase B Plant; · Buildings; · Electrical systems; · Instrument and control systems; and · Metering system.
Renovation work for existing Mirfa Plant buildings, such as external and internal re- painting, exchange of floorings and tiling for walls and floors exchange of suspended ceilings, exchange of cladding, re-painting of steel structure, and exchange of doors and windows, will be completed during normal maintenance operations.
The Mirfa IWPP is to have a net power capacity of 1,600 MW and a desalination capacity of 52.5 MIGD. To achieve this, the plant will consist of:
· The existing Fisia MSF units will be transferred from Phase B of the Existing Mirfa Plant, · A new 1,240 MW CCGT plant running with Ansaldo GTs; · The existing Fisia MSF Units (supplied with steam from the new CCGT plant); · A 360 MW OCGT plant utilising the four General Electric (GE) 9E GT packages and existing inventory; and · A new 30 MIGD reverse osmosis (RO) plant supplied by Degremont.
The four OCGTs are required to be in commercial operation by 31 July 2016, as well as the new RO Plant. Two of the new CCGTs are required to be in commercial operation in open-cycle configuration for an Early Power period which is scheduled to commence on 31 July 2016 and continue up to and including 31 October 2016. The scheduled Project Commercial Operation Date for the entire Mirfa IWPP is 8 April 2017.
1.2 Summary of Findings
Assessment of the potential environmental impacts associated with the Mirfa IWPP project has been carried out in accordance with the Environment Agency – Abu Dhabi Technical Guidance Document for Environmental Impact Assessment (2010). Baseline data for this report has been compiled from available published information, URS Corporation – Abu Dhabi (URS) in-house data from previous studies of the Mirfa site, and field investigations performed for this project. The relevant reports used in this Environmental and Social Impact Assessment (ESIA) are listed below:
· Mirfa Power Plant Expansion EIA (January 2010); and · Mirfa Rehabilitation Project EIA (July 2010).
The findings of these assessments are summarised below. Impact ranking has been carried out as per EAD guidelines as detailed in Section 5. The impact assessments show the residual impacts after the appropriate mitigations are implemented.
1.2.1 Air Quality
The IWPP has the potential to impact air quality in the following ways:
· Emissions from operation of fuel consuming vehicles and equipment; · Combustion and fugitive emissions from the operation of the power and desalination plant; · Greenhouse gas emissions; and · Emissions from accidental events.
The baseline air quality is detailed in Section 5.1.1. A summary table of the impact assessment stages detailed in Sections 5.1.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
1.2.2 Marine Water
The Project has the potential to impact marine water in the following ways:
· Used seawater discharge into the marine environment; · Wastewater discharge into the marine environment; and · Storm water run-off into the marine environment.
The baseline for marine water quality is detailed in Section 5.2.1. A summary table of the impact assessment stages is detailed in Section 5.2.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
1.2.3 Waste Management
The IWPP has the potential impacts from wastes as a result of inappropriate handling, storage, and disposal of:
· Solid Waste; · Liquid waste; and · Hazardous wastes.
A description of proposed waste management practices is detailed in Section 5.3.1. A summary table of the impact assessment stages detailed in Sections 5.3.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
1.2.4 Soil and Groundwater
The IWPP has the potential to impact soil and groundwater in the following ways:
· Disturbance to site soils; · Contamination of soil; and · Contamination of shallow groundwater.
Baseline soil and groundwater conditions are detailed in Section 5.4.1. A summary table of the impact assessment stages detailed in Sections 5.4.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
1.2.5 Marine Ecology
The Project has the potential to impact marine ecology in the following ways:
· Direct physical loss of habitat; and · Effects of effluent discharge on marine ecology;
The baseline for marine ecology is detailed in Section 5.5.1. A summary table of the impact assessment stages is detailed in Section 5.5.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
1.2.6 Terrestrial Ecology
The Project has the potential to impact terrestrial ecology in the following ways:
· Loss of habitat; and · Disturbance to flora and fauna.
The baseline for terrestrial ecology is detailed in Section 5.6.1. A summary table of the impact assessment stages is detailed in Section 5.6.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
1.2.7 Noise
The IWPP has the potential impacts from noise in the following ways:
· Emissions from operation of vehicles and temporary equipment; · Emissions from operation of plant; and · Emissions from abnormal events.
Baseline noise levels are detailed in Section 5.7.1. A summary table of the impact assessment stages detailed in Sections 5.7.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
1.2.8 Traffic
The IWPP has the potential impact from traffic by increasing in traffic load on local roads.
Baseline traffic conditions are detailed in Section 5.8.1. A summary table of the impact assessment stages detailed in Sections 5.8.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
1.2.9 Socioeconomic
The Project has the potential to impact socioeconomics in the following ways:
· Land use and community impacts; · Social impacts; and · Economic impacts.
Baseline socioeconomics conditions are detailed in Section 5.9.1. A summary table of the impact assessment stages is detailed in Section 5.9.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
1.2.10 Other Environmental Components
The Project has the potential to have other impacts in the following ways:
· Archaeology and paleontology; and · Visual amenity.
The baseline for these other impacts is detailed in Section 5.10.1. A summary table of the impact assessment stages is detailed in Section 5.10.2 is provided below. Detailed descriptions of mitigation and monitoring measures are provided only for those residual risks deemed of High or higher significance.
M=Magnitude P=Permanence R=Reversibility C=Cumulative
Selected Mitigations
|